Bentley Motors has completed a 2.8 MW rooftop solar installation at its new Paint Shop in Crewe, England, using XAG P150 Max cargo drones to lift 2,030 photovoltaic panels onto four roofs. Bentley announced the project on November 23. The drones placed roughly one panel per minute, and Bentley said the method more than halved the installation time compared with conventional lifting equipment.
Each 515 W JA Solar panel weighs about 30 kg, and the panels lifted in this project totalled more than 55 tonnes. They were carried one at a time in a purpose-made lifting bag using the XAG RevoSling cargo system, so no changes to the panels were needed. The lifting phase took just over a week, with around 10 tonnes of material moved on a typical working day.
The installation was delivered by Push Power Limited with funding partner Finlight. The flights were carried out by AutoSpray Systems and members of the AutoSpray Pilot Network under an Operational Authorisation from the UK Civil Aviation Authority, assessed with the SORA method at SAIL II. The new array brings the number of solar panels at the Crewe site to more than 35,000.
For buyers of heavy-lift cargo drones, the project shows a construction logistics use beyond agriculture: moving building materials directly to a roof without cranes or scaffold hoists, and reducing manual handling at height. Our team can help buyers compare XAG cargo platforms and lifting accessories for site logistics projects.